We monitor Network Rail’s planning and delivery of enhancements (large scale projects delivering new infrastructure capabilities), to:
- assess the risk to successful delivery of timetable changes and the resultant impact on passengers;
- understand the effect of enhancements on the rest of Network Rail’s business (including operations, maintenance and renewals);
- publicly report on Network Rail’s progress delivering enhancements and highlighting reasons for changes to its plan; and
- provide an understanding of Network Rail’s broader capability across its business to the funders of enhancements.
We provide advice to Transport Scotland on the cost of projects and hold Network Rail to account to deliver key milestones, for Scotland enhancements. However, we have agreed with Department for Transport that we will not monitor the cost efficiency of the projects it funds or take action in relation to specific milestones for these projects.
We protect the interests of Network Rail’s customers and stakeholders by making sure they have the opportunity to comment on the impact of changes to Network Rail’s plans.
We also provide guidance on the Investment Framework to inform third parties considering investment in the railway, we approve template contracts and we provide advice where required.
Our Roles and responsibilities for enhancements in CP7 document provides more details about ORR’s role in the current 5-year control period, in relation to that of DfT, Transport Scotland and Network Rail.
What are the enhancement projects Network Rail is committed to deliver?
Collapse accordion
Open accordion
Network Rail's licence requires them to publish a delivery plan that sets out its obligations for enhancement projects. This allows train operators to plan their businesses and funders to plan their finances with a reasonable degree of assurance.
Network Rail publishes a list of enhancements projects in its Enhancements Delivery Plan. If Network Rail needs to make changes to the Enhancements Delivery Plans, for example if a delivery milestone has to be delayed, Network Rail must agree it with their funders through a Change Control process. ORR reviews these Change Controls to make sure that all the affected stakeholders (such as train companies and local councils) have been consulted and that Network Rail are taking any concerns into account.
How is Network Rail performing on delivering enhancement projects and improving its capability?
Collapse accordion
Open accordion
We report on Network Rail’s performance on delivering enhancement projects every 6 months in our Network Rail Monitor.
In addition, we sometimes use the Independent Reporter to complete a detailed review of specific projects or delivery concerns. Previous reviews have included Network Rail’s delivery of the Stirling-Dunblane-Alloa project and Edinburgh Glasgow Improvement Programme’s Target Cost. Details are available on our Independent reporters webpage.
We found Network Rail in breach of its licence in October 2015 regarding its planning and delivery of its enhancements programme. Since 2015, Network Rail has been working on many improvements to its capability to manage enhancements, including the Enhancements Improvement Programme (EIP).
We commissioned the Independent Reporter to complete reviews of some areas where Network Rail was looking to improve its capability in CP5, including the Enhancements Improvement Programme and its management of complex programmes. Details are available on our Independent reporters webpage.
In 2018 we began piloting a new method to assess Network Rail’s capability on enhancements. We will report on Network Rail’s progress with improving its capability in our Network Rail Monitor.
In late 2022, at a time when the industry was facing challenges around inflation and industrial relations, we looked into concerns raised by project staff about workload and inefficiency within Network Rail projects. Overall, we found that all the Network Rail regions were aware of the local issues and they were making changes which should reasonably address these issues. However these changes would not be complete until the start of CP7, so in October 2023 we wrote a letter to Network Rail, summarising what we had found and noting that we would carry out a follow-up review at the start of CP7.
How is the efficiency of Network Rail’s enhancements costs reviewed in Scotland?
Collapse accordion
Open accordion
In order to assist the Scottish Government in taking an informed decision on whether Network Rail’s proposed costs represent good value, ORR has been tasked by Transport Scotland with assessing the efficiency of Network Rail’s enhancement’s estimates.
As part of the new pipeline approach to committing to and funding enhancements, Network Rail will need to submit its developing business cases and estimates to a series of Scottish Government investment panels for approval. ORR will carry out an efficiency review of each estimate at an appropriate stage of development and ahead of an agreed panel date. The estimate review will assess whether the costs are justified, in-line with benchmarks and industry norms, have been developed using sound principles and whether they contain inefficiencies or unsupported cost. A report will be submitted to both Network Rail and Transport Scotland outlining our views on the efficiency of the proposals and any areas of concern within the estimate that require further focus.
ORR will not be setting a target cost or incentivising Network Rail to deliver the project efficiently.
ORR Change Control quarterly decision letters (CP5)
Collapse accordion
Open accordion
In CP5, ORR provided Network Rail with a quarterly letter, outlining our decisions on any changes to the enhancements delivery plan. These letters are available below:
- Enhancements Delivery Plan (EDP) change control: January – March 2019
- Enhancements Delivery Plan (EDP) change control: October - December 2018
- Enhancements Delivery Plan (EDP) change control: July - September 2018
- Enhancements Delivery Plan (EDP) change control: April - June 2018
- Enhancements Delivery Plan (EDP) change control: January - March 2018
- Enhancements Delivery Plan (EDP) change control: October - December 2017
- Enhancements Delivery Plan (EDP) change control: July - September 2017
- Enhancements Delivery Plan (EDP) change control: July 2017
- Enhancements Delivery Plan (EDP) change control: April - June 2017
- Enhancements Delivery Plan (EDP) change control: January - March 2017
- Enhancements Delivery Plan (EDP) change control: October - December 2016
- Enhancements Delivery Plan (EDP) change control: April - September 2016
- Enhancements Delivery Plan (EDP) change control: March 2016
- Enhancements Delivery Plan (EDP) change control: October 2015
- Enhancements Delivery Plan (EDP) change control: June 2015
- Enhancements Delivery Plan (EDP) change control: March 2015
- Enhancements Delivery Plan (EDP) change control: December 2014
- Enhancements Delivery Plan (EDP) change control: September 2014
- Enhancements Delivery Plan (EDP) change control: June 2014
Regulated milestone status summaries (attachments to ORR Monitor)
Collapse accordion
Open accordion
In CP5 we also published reports that listed the project milestones for each 6 month period showing which milestones were achieved, missed or revised.
- Network Rail Enhancements Delivery Plan Regulated Milestones 2018-19 H1 (01st April 2018 to 14th October 2018)
- Network Rail Enhancements Delivery Plan Regulated Milestones 2017-18 H2 (15th October 2017 – 31st March 2018)
- Network Rail enhancements delivery plan regulated milestones 2017-18 H1 (1st April 2017 – 14th October 2017) - December 2017
- Network Rail Enhancements Delivery Plan Regulated Milestones 2016-17 H2 (1 October 2016 – 31 March 2017) - July 2017
- Enhancements Delivery Plan - Regulatory Change Control - Control Period 5 - Purpose, process map and milestone reporting criteria - July 2017
- Network Rail Enhancements Delivery Plan (EDP) regulated milestones 2016-17 H1
- Network Rail Enhancements Delivery Plan (EDP) regulated milestones 2015-16 - 5 July 2016
- Network Rail Enhancements Delivery Plan Regulated Milestones 2018-19 H2 (15st October 2018 to 31st March 2019)